Section 246-359-090. Issuing and maintaining a construction permit.  


Latest version.
  • (1) The department of health will issue a construction permit when:
    (a) Construction documents are approved according to WAC 246-359-080; and
    (b) Permit and inspection fees are paid according to WAC 246-359-990.
    (2) Construction can begin after the applicant is issued a construction permit by the department of health;
    (3) The following conditions, at a minimum, must be met during construction:
    (a) The "inspection record card" must be posted in a visible location at the worksite and be readily accessible to the inspector at the worksite; and
    (b) The approved plans must be readily available to the inspector during all scheduled inspections.
    (4) The department of health will void the permit and the applicant's right to continue construction when:
    (a) The plans are changed, modified or altered without prior approval by the department of health as specified in WAC 246-359-080;
    (b) Any deviation in construction or design is made from the approved plans; and
    (c) The inspection record card and the approved plans are not readily and easily available to the inspector.
    [Statutory Authority: Chapter 70.114A RCW and RCW 43.70.334 through 43.70.340. WSR 15-13-091, § 246-359-090, filed 6/15/15, effective 1/1/16. Statutory Authority: RCW 70.114A.081. WSR 99-03-065, § 246-359-090, filed 1/18/99, effective 2/18/99.]
Chapter 70.114A RCW and RCW 43.70.334 through 43.70.340. WSR 15-13-091, § 246-359-090, filed 6/15/15, effective 1/1/16. Statutory Authority: RCW 70.114A.081. WSR 99-03-065, § 246-359-090, filed 1/18/99, effective 2/18/99.

Rules

246-359-080,246-359-990,246-359-080,