Section 173-95A-540. Step process for facilities.  


Latest version.
  • (1) The step process is required for facilities construction projects. The process begins with site-specific planning, and continues through design to construction or implementation. At the time of application, all previous steps must be approved by the department. Draft documents must be sent to the department's engineers at least sixty days before end of application cycle for approval by end of application cycle. Funding for one step does not guarantee the future funding of subsequent steps.
    (2) The step process includes the following:
    (a) Planning (step one): Step one involves the preparation of a site-specific facilities plan that identifies the cost-effective alternatives for addressing a water pollution control problem. There is no prerequisite for planning. If there is an existing engineering report, it must be upgraded to a facilities plan;
    (b) Design (step two): Step two includes the preparation of plans and specifications for use in construction. These must be based on the preferred cost-effective alternative identified in the facilities plan. Facilities plans must be approved by the department before an application for design can be considered for funding. Facilities plans approved by the department more than two years before the close of the application period must contain evidence of recent review by the department to ensure the document reflects current conditions; and
    (c) Construction (step three): Step three includes the actual building of facilities based on the approved design. Design must be approved by the department before an application for construction can be considered for funding. The applicant must also have a current rate study that includes the proposed project before an application for construction can be considered for funding. The utility rate proposed in the rate study must be adequate to pay for O&M, debt service, and replacement of short lived assets, and any other associated project costs. The applicant must have an adopted fee ordinance based on the current rate study that includes the proposed project before the department will sign a loan agreement.
    (3) Combined steps for smaller design-bid-construct projects (step four): In some cases, design and construction may be combined into one loan. Step four applicants must demonstrate that step two (design) can be completed and approved by the department within one year of the effective date of the funding agreement. The applicant must also complete a rate study that includes the proposed project and adopt a fee ordinance based on the rate study before the department will approve plans and specifications as required in WAC 173-98-560, approval of plans and specifications. The utility rate proposed in the rate study must be adequate to pay for O&M, debt service, and replacement of short lived assets, and any other associated project costs. The total project costs for step four projects must be five million dollars or less.
    (4) Step deviations. During the application phase of the funding cycle, the department may allow an applicant to deviate from the traditional step requirements if:
    (a) The Washington state department of health has declared a public health emergency; and
    (b) The proposed project would remedy this situation.
    No loan agreement will be signed until all previous steps have been completed and approved by the department.
    [Statutory Authority: Chapter 90.50A RCW, RCW 90.48.035, and 43.21A.080. WSR 11-20-036 (Order 10-14), § 173-95A-540, filed 9/27/11, effective 10/28/11. Statutory Authority: RCW 90.48.035. WSR 07-14-096 (Order 05-16), § 173-95A-540, filed 6/29/07, effective 7/30/07.]
Chapter 90.50A RCW, RCW 90.48.035, and 43.21A.080. WSR 11-20-036 (Order 10-14), § 173-95A-540, filed 9/27/11, effective 10/28/11. Statutory Authority: RCW 90.48.035. WSR 07-14-096 (Order 05-16), § 173-95A-540, filed 6/29/07, effective 7/30/07.