Section 173-360-830. Under-dispenser containment.


Latest version.
  • (1) Applicability. UST systems connected to a dispenser must be equipped with under-dispenser containment meeting the requirements of this section if the dispenser, dispenser system, or underground piping connected to the dispenser system is installed or replaced after October 1, 2012.
    (2) Performance standards. Under-dispenser containment must be designed, constructed, and installed to:
    (a) Be liquid-tight on its sides, bottom, and at any penetrations; and
    (b) Allow for visual inspection and access to the components in the containment system.
    (3) Installation and reporting. Installation of under-dispenser containment must be:
    (a) Performed by an UST supervisor certified to install UST systems under Part 6 of this chapter;
    (b) Performed in accordance with the manufacturer's instructions; and
    (c) Certified and reported in accordance with WAC 173-360-630 (2)(a).
    [Statutory Authority: Chapter 90.76 RCW. WSR 12-17-041 (Order 08-08), § 173-360-830, filed 8/8/12, effective 10/1/12.]
Chapter 90.76 RCW. WSR 12-17-041 (Order 08-08), § 173-360-830, filed 8/8/12, effective 10/1/12.