Section 480-90-158. Service connections.  


Latest version.
  • (1) The gas utility must furnish, install, and maintain piping and other fittings to the customer's piping up to the point of delivery. The point of delivery is at the outlet of the meter or at the connection to a customer's piping, whichever is farther downstream.
    (2) The customer may be required to pay for or install any service connection such as pipes and fittings in compliance with the gas utility's standards and filed tariff(s). The service piping and fittings up to the point of delivery will become the property of the utility, which must accept all responsibility for future maintenance and operations in accordance with its filed tariffs.
    [Statutory Authority: RCW 80.01.040 and 80.04.160. WSR 01-11-003 (Docket No. UG-990294, General Order No. R-484), § 480-90-158, filed 5/3/01, effective 6/3/01.]
RCW 80.01.040 and 80.04.160. WSR 01-11-003 (Docket No. UG-990294, General Order No. R-484), § 480-90-158, filed 5/3/01, effective 6/3/01.