Washington Administrative Code (Last Updated: November 23, 2016) |
Title 480. Utilities and Transportation Commission |
Chapter 480-75. Hazardous liquid pipelines—Safety. |
Section 480-75-390. Valve spacing and rapid shutdown.
Latest version.
- (1) Each pipeline company must have procedures to rapidly locate and isolate reportable releases from its pipeline.(2) When determining the type of valve to be used, its location, and its shut-off time, each pipeline company must consider the following:(a) Terrain;(b) Geohazards;(c) Drainage; and(d) Type and condition of the pipe.(3) Whenever a pipeline company installs a new rapid shutdown valve, the pipeline company must conduct a surge analysis to ensure that the surge pressure in the pipeline will not exceed one hundred ten percent of the maximum operating pressure as a result of a rapid valve closure.[Statutory Authority: RCW 80.01.040, 80.04.060, 81.88.040. WSR 08-12-045 (Docket PL-070974, General Order R-548), § 480-75-390, filed 5/30/08, effective 6/30/08. Statutory Authority: RCW 80.01.040 and 80.04.160. WSR 03-01-064 (Docket No. TO-000712, General Order No. R-508), § 480-75-390, filed 12/12/02, effective 1/12/03.]
RCW 80.01.040, 80.04.060, 81.88.040. WSR 08-12-045 (Docket PL-070974, General Order R-548), § 480-75-390, filed 5/30/08, effective 6/30/08. Statutory Authority: RCW 80.01.040 and 80.04.160. WSR 03-01-064 (Docket No. TO-000712, General Order No. R-508), § 480-75-390, filed 12/12/02, effective 1/12/03.