Section 480-107-025. Contents of the solicitation.
Latest version.
- (1) The RFP must identify the resource block, consisting of the overall amount and duration of power the utility is soliciting, the initial estimate of avoided cost schedule as calculated in WAC 480-107-055 Avoided cost schedule, and any additional information necessary for potential bidders to make a complete bid.(2) The RFP must document that the size of the resource block is consistent with the range of estimated new resource needs identified in the utility's integrated resource plan.(3) The RFP must explain general evaluation and ranking procedures the utility will use in accordance with WAC 480-107-035 Project ranking procedure. The RFP must also specify any minimum criteria that bidders must satisfy to be eligible for consideration in the ranking procedure.(4) The RFP must specify the timing of process including the solicitation period, the ranking period, and the expected selection period.(5) The RFP must identify all security requirements and the rationale for them.(6) Utilities are encouraged to consult with commission staff during the development of the RFP. Utilities, at their own discretion, may submit draft RFPs for staff review prior to formally submitting an RFP to the commission.
Rules
480-107-055,480-107-035,