Washington Administrative Code (Last Updated: November 23, 2016) |
Title 479. Transportation Improvement Board |
Chapter 479-10. Preservation programs. |
Section 479-10-420. Work eligible for streetlight program funds.
Latest version.
- Eligible projects include:(1) Replacement of existing luminaires;(2) Replacement of existing streetlight infrastructure may be included when:(a) The infrastructure is required for installation of new luminaires; and(b) The cost is determined by TIB to be appropriately borne by the city.(3) Placement of new lights when necessary as determined by the executive director or board.[Statutory Authority: Chapter 47.26 RCW. WSR 15-22-052, § 479-10-420, filed 10/29/15, effective 11/29/15.]
Chapter 47.26 RCW. WSR 15-22-052, § 479-10-420, filed 10/29/15, effective 11/29/15.