Section 479-05-212. The stages of delayed projects.
Latest version.
- For TIB funded projects, there are two stages of delay:(1) Stage 1 delay - If the project does not meet the project target date per WAC 479-05-211.(2) Stage 2 delay - If the project does not meet the revised bid date as agreed to under Stage 1 delay under WAC 479-05-213(1), or one year after being designated as a Stage 1 delayed project.[Statutory Authority: Chapter 47.26 RCW. WSR 12-08-060, § 479-05-212, filed 4/3/12, effective 5/4/12; WSR 07-18-050, § 479-05-212, filed 8/30/07, effective 9/30/07.]
Chapter 47.26 RCW. WSR 12-08-060, § 479-05-212, filed 4/3/12, effective 5/4/12; WSR 07-18-050, § 479-05-212, filed 8/30/07, effective 9/30/07.
Rules
479-05-211,479-05-213,