Section 479-05-204. If an increase is not approved.  


Latest version.
  • An agency request for an increase in funds may go to either the executive director or the board, as described in WAC 479-05-202, depending on the size of the request:
    (1) If the executive director hears the request and does not approve it, the local agency may:
    (a) Proceed with the project, paying for any additional costs with local or other funds;
    (b) Withdraw the request for participation;
    (c) Request a formal review of the executive director's decision by the board; or
    (d) Submit a request to the executive director to reduce the scope of the project as provided in WAC 479-05-052.
    (2) If the board hears the request and does not approve it, the local agency may:
    (a) Proceed with the project, paying for additional costs;
    (b) Withdraw the request for participation; or
    (c) Request a scope modification or reduction as provided in WAC 479-05-052.
    In either case, the project will need to retain a usable and functional improvement to be granted a scope reduction.
    [Statutory Authority: Chapter 47.26 RCW. WSR 07-18-050, § 479-05-204, filed 8/30/07, effective 9/30/07.]
Chapter 47.26 RCW. WSR 07-18-050, § 479-05-204, filed 8/30/07, effective 9/30/07.

Rules

479-05-202,479-05-052,479-05-052,