Washington Administrative Code (Last Updated: November 23, 2016) |
Title 463. Energy Facility Site Evaluation Council |
Chapter 463-61. Electrical transmission facilities. |
Section 463-61-100. Applications for site certification.
Latest version.
- (1) An application for site certification may be submitted when the preapplication process is completed. The preapplication process shall be complete when:(a) EFSEC has held one or more public meetings under WAC 463-61-060(3); and(b) Negotiations between affected cities, towns, and/or counties have been conducted and a corridor has been agreed on; or(c) Negotiations under WAC 463-61-080 have been conducted but the preapplicant, cities, towns, and/or counties have not agreed on a corridor and EFSEC has determined that negotiations have failed.
Rules
463-61-060,463-61-080,463-60,