Washington Administrative Code (Last Updated: November 23, 2016) |
Title 463. Energy Facility Site Evaluation Council |
Chapter 463-61. Electrical transmission facilities. |
Section 463-61-040. Initial consultation.
Latest version.
- Prior to filing a preapplication request under WAC 463-61-050, the preapplicant shall meet and consult with the EFSEC staff concerning the proposed project. Topics for discussion shall include but not be limited to:(1) The nature of the project, the contents of the preapplication request and the status of the preapplicant's progress toward obtaining information and data regarding the project.(2) A discussion of whether a third-party contractor is likely to be needed to prepare an environmental documentation for the project.(3) Development of a preapplication plan to be filed with a preapplication request.(4) The coordination of the public informational meeting.
Rules
463-61-050,