Section 463-60-160. Proposal—Electrical transmission facilities.  


Latest version.
  • (1) Prior to submitting an application for site certification for an electric transmission facility under RCW 80.50.060(3) an applicant shall follow the procedure as set in chapter 463-61 WAC.
    (2) An application for an electric transmission facility shall include the information required by this chapter unless the requirement may not be applicable to such a facility.
    (3) An application for an electrical transmission facility shall include the results of any preapplication negotiations including any agreements between the applicant and cities, towns, or counties where the electrical transmission facility is proposed to be located.
    [Statutory Authority: Chapter 80.50 RCW and RCW 80.50.040. WSR 09-05-067, § 463-60-160, filed 2/13/09, effective 3/16/09.]
Chapter 80.50 RCW and RCW 80.50.040. WSR 09-05-067, § 463-60-160, filed 2/13/09, effective 3/16/09.

Rules

463-61,