Washington Administrative Code (Last Updated: November 23, 2016) |
Title 463. Energy Facility Site Evaluation Council |
Chapter 463-58. Charges for independent consultant study, regular and expedited application processing, electrical transmission preapplications, determining compliance and potential site study. |
Section 463-58-060. Costs for potential site studies.
Latest version.
- Ten thousand dollars shall accompany the study request and be a condition precedent to any action by the council. In the event that the council determines that the initial fee of ten thousand dollars is insufficient to adequately fund the potential site study, the council shall so advise the potential applicant and shall furnish an estimate of the supplemental funds needed to complete the study. In no event shall the study be allowed to continue if the potential applicant has not agreed to pay the cost.[Statutory Authority: Chapter 80.50 RCW and RCW 80.50.040. WSR 09-05-067, § 463-58-060, filed 2/13/09, effective 3/16/09. Statutory Authority: RCW 80.50.040 (1) and (12). WSR 04-21-013, § 463-58-060, filed 10/11/04, effective 11/11/04. Statutory Authority: RCW 80.50.071. WSR 78-05-054 (Order 78-2), § 463-58-060, filed 4/26/78.]
Chapter 80.50 RCW and RCW 80.50.040. WSR 09-05-067, § 463-58-060, filed 2/13/09, effective 3/16/09. Statutory Authority: RCW 80.50.040 (1) and (12). WSR 04-21-013, § 463-58-060, filed 10/11/04, effective 11/11/04. Statutory Authority: RCW 80.50.071. WSR 78-05-054 (Order 78-2), § 463-58-060, filed 4/26/78.