  • (1) Construction documents must be resubmitted for review as a new project according to current requirements if construction:
    (a) Has not started within one year from the date of approval; or
    (b) Is not completed within two years from the date of approval.
    (2) To obtain an extension beyond two years, a written request must be submitted and approved thirty days prior to the end of the two-year period.