Section 388-96-022. Due dates for cost reports.  


Latest version.
  • (1) The contractor shall submit annually a complete report of costs and financial conditions of the contractor prepared and presented in a standardized manner and in accordance with this chapter and chapter 74.46 RCW.
    (2) Not later than March 31st of each year, each contractor shall submit to the department an annual cost report for the period from January 1st through December 31st of the preceding year.
    (3) Not later than one hundred twenty days following the termination or assignment of a contract, the terminating or assigning contractor shall submit to the department a cost report for the period from January 1st through the date the contract was terminated or assigned.
    (4) If the cost report is not properly completed or if it is not received by the due date established in subsection (2) or (3) of this section, all or part of any payments due under the contract may be withheld by the department until such time as required cost report is properly completed and received.
    (5) The department may impose civil fines, or take adverse rate action against contractors and former contractors who do not submit properly completed cost reports by the applicable due date established in subsection (2) or (3) of this section.
    [Statutory Authority: Chapter 74.46 RCW, 2010 1st sp.s. c 34, and 2010 1st sp.s. c 37 § 958. WSR 11-05-068, § 388-96-022, filed 2/14/11, effective 2/26/11.]
Chapter 74.46 RCW, 2010 1st sp.s. c 34, and 2010 1st sp.s. c 37 § 958. WSR 11-05-068, § 388-96-022, filed 2/14/11, effective 2/26/11.