Section 197-11-545. Effect of no comment.  


Latest version.
  • (1) Consulted agencies. If a consulted agency does not respond with written comments within the time periods for commenting on environmental documents, the lead agency may assume that the consulted agency has no information relating to the potential impact of the proposal as it relates to the consulted agency's jurisdiction or special expertise. Any consulted agency that fails to submit substantive information to the lead agency in response to a draft EIS is thereafter barred from alleging any defects in the lead agency's compliance with Part Four of these rules.
    (2) Other agencies and the public. Lack of comment by other agencies or members of the public on environmental documents, within the time periods specified by these rules, shall be construed as lack of objection to the environmental analysis, if the requirements of WAC 197-11-510 are met.
    [Statutory Authority: RCW 43.21C.110. WSR 84-05-020 (Order DE 83-39), § 197-11-545, filed 2/10/84, effective 4/4/84.]
RCW 43.21C.110. WSR 84-05-020 (Order DE 83-39), § 197-11-545, filed 2/10/84, effective 4/4/84.

Rules

197-11-510,