Washington Administrative Code (Last Updated: November 23, 2016) |
Title 194. Commerce, Department of (Energy) |
Chapter 194-22. Washington state curtailment plan for electric energy. |
Section 194-22-090. Curtailment administration—Excess power consumption.
Latest version.
- Excess power consumption is calculated at each utility's discretion as one of two values: Actual or estimated load minus curtailment target; or weather-normalized load minus curtailment target. Enforcement measures (see WAC 194-22-110, mandatory curtailment enforcement) will only be assessed on excess power consumption if a consumer's actual, estimated or weather-normalized load is greater than the threshold consumption level.[Statutory Authority: RCW 43.21F.045. WSR 94-20-103, § 194-22-090, filed 10/4/94, effective 11/4/94.]
RCW 43.21F.045. WSR 94-20-103, § 194-22-090, filed 10/4/94, effective 11/4/94.
Rules
194-22-110,