Section 173-98-520. Ceiling amounts.  


Latest version.
  • (1) Green project reserves category:
    (a) No more than fifty percent of the revolving fund in this category will be available to any one applicant per funding cycle; and
    (b) The ceiling amount for forgivable principal provided for eligible green project reserves projects is up to fifty percent of total eligible project costs. If demand is limited for green project reserves projects, the ceiling amount may be raised to fully use available funding.
    (2) Preconstruction category:
    (a) No more than twenty percent of the revolving fund in this category will be available to any one applicant per funding cycle.
    (b) The ceiling amount for a forgivable principal loan provided for financial hardship for WAC 173-98-330 is up to fifty percent of the eligible project costs. If demand is limited for projects eligible for preconstruction category, the ceiling amount may be raised to fully use available funding.
    (c) The ceiling amount for this category applies to the combined total of all preconstruction elements for loans and forgivable principal loans.
    (3) Water pollution control facilities category:
    (a) No more than fifty percent of the revolving fund in this category will be available to any one applicant per funding cycle;
    (b) The ceiling amount for a forgivable principal loan provided for financial hardship for WAC 173-98-330 is five million dollars. If a forgivable principal loan is provided for a hardship project in conjunction with a centennial program grant award for hardship, then the ceiling amount for the combined forgivable principal loan and centennial program grant is five million dollars; and
    (c) No more than five million dollars is available for each smaller combined design-construct project (step four). See WAC 173-98-530 for information on smaller combined design-construct projects (step four).
    (4) Water pollution control activities category: Not more than fifty percent of the revolving fund in this category will be available to any one applicant per funding cycle.
    (5) Water pollution control facilities construction bid overruns:
    (a) If the low responsive responsible construction bid(s) exceeds the engineer's estimate of construction costs, the department may approve funding increases for up to ten percent of the engineer's original estimate;
    (b) The ceiling amounts that were established in the fiscal year in which the project was offered funding apply; and
    (c) First priority for funding bid overruns will be given to hardship communities based on the severity of financial need.
    (6) Water pollution control facilities construction change orders:
    (a) The department may approve funding for change orders for up to five percent of the eligible portion of the low responsive responsible construction bid(s);
    (b) The ceiling amounts that were established in the fiscal year in which the project was offered funding apply; and
    (c) First priority for funding change orders will be given to hardship communities based on the severity of financial need.
    (7) If a project qualifies for both hardship funding and green project reserves funding, then the ceiling amount for total forgivable principal and centennial grant funding for the project is the combined ceiling amount of both hardship and green project reserves categories.
    [Statutory Authority: Chapter 90.50A RCW, RCW 90.48.035, and 43.21A.080. WSR 11-20-036 (Order 10-14), § 173-98-520, filed 9/27/11, effective 10/28/11. Statutory Authority: RCW 90.48.035. WSR 07-14-096 (Order 05-16), § 173-98-520, filed 6/29/07, effective 7/30/07.]
Chapter 90.50A RCW, RCW 90.48.035, and 43.21A.080. WSR 11-20-036 (Order 10-14), § 173-98-520, filed 9/27/11, effective 10/28/11. Statutory Authority: RCW 90.48.035. WSR 07-14-096 (Order 05-16), § 173-98-520, filed 6/29/07, effective 7/30/07.

Rules