Section 173-360-310. Upgrading requirements for existing UST systems.  


Latest version.
  • (1) Alternatives allowed. Not later than December 22, 1998, all existing UST systems shall comply with one of the following requirements:
    (a) New UST system performance standards under WAC 173-360-305;
    (b) The upgrading requirements in subsections (2) through (4) of this section; or
    (c) Closure requirements under WAC 173-360-380 through 173-360-398, including applicable requirements for corrective action under WAC 173-360-399.
    (2) Tank upgrading requirements. Steel tanks shall be upgraded by a certified UST supervisor to meet one of the following requirements in accordance with a code of practice developed by a nationally recognized association or independent testing laboratory:
    (a) Interior lining. A tank may be upgraded by internal lining if:
    (i) The lining is installed in accordance with the requirements of WAC 173-360-325; and
    (ii) Within ten years after lining, and every five years thereafter, the lined tank is internally inspected and found to be structurally sound with the lining still performing in accordance with original design specifications, unless cathodic protection is also installed within ten years of lining the tank, as specified in WAC 173-360-310 (2)(c).
    (b) Cathodic protection. A tank may be upgraded by cathodic protection if the cathodic protection system meets the requirements of WAC 173-360-305 (1)(b)(ii), (iii), and (iv) and the integrity of the tank is ensured using one of the following methods:
    (i) The tank is internally inspected and assessed to ensure that the tank is structurally sound and free of corrosion holes prior to installing the cathodic protection system; or
    (ii) The tank has been installed or internally lined for less than ten years and is monitored monthly for releases in accordance with WAC 173-360-345 (6)(e) through (j); or
    (iii) The tank has been installed or internally lined for less than ten years and is assessed for corrosion holes by conducting two tightness tests that meet the requirements of WAC 173-360-345 (6)(d). The first tightness test shall be conducted prior to installing the cathodic protection system. The second tightness test shall be conducted between three and six months following the first operation of the cathodic protection system; or
    (iv) The tank is assessed for corrosion holes by a method that is determined by the department or delegated agency to prevent releases in a manner that is no less protective of human health and the environment than subsection (2)(b)(i) through (iii) of this section.
    (c) Internal lining combined with cathodic protection. A tank may be upgraded by both internal lining and cathodic protection if:
    (i) The lining is installed in accordance with the requirements of WAC 173-360-325; and
    (ii) The cathodic protection system is installed within ten years of the tank being lined and meets the requirements of WAC 173-360-305 (1)(b)(ii), (iii), and (iv).
    Note:
    The following codes and standards may be used to comply with this section:
    (A) American Petroleum Institute Publication 1631, "Recommended Practice for the Interior Lining of Existing Steel Underground Storage Tanks";
    (B) National Leak Prevention Association Standard 631, "Spill Prevention, Minimum 10 Year Life Extension of Existing Steel Underground Tanks by Lining Without the Addition of Cathodic Protection";
    (C) National Association of Corrosion Engineers Standard RP-02-85, "Control of External Corrosion on Metallic Buried, Partially Buried, or Submerged Liquid Storage Systems";
    (D) American Petroleum Institute Publication 1632, "Cathodic Protection of Underground Petroleum Storage Tanks and Piping Systems"; and
    (E) Steel Tank Institute Publication STI F894-91 "Specifications for External Corrosion Protection FRP Composite Underground Steel Storage Tanks."
    (3) Piping upgrading requirements. Metal piping that routinely contains regulated substances and is in contact with the ground shall be cathodically protected in accordance with a code of practice developed by a nationally recognized association or independent testing laboratory and shall meet the requirements of WAC 173-360-305 (2)(b)(ii), (iii), and (iv).
    Note:
    The codes and standards listed in the note following WAC 173-360-305 (2)(b) may be used to comply with this requirement.
    (4) Spill and overfill prevention equipment. To prevent spilling and overfilling associated with transfer of regulated substances to the UST system, all existing UST systems shall comply with new UST system spill and overfill prevention equipment requirements specified in WAC 173-360-305(3), except that an UST system that is filled by transfers of no more than twenty-five gallons at a time is not required to use spill and overfill prevention equipment.
    (5) Certified UST supervisors who perform any of the tank services described in this section shall certify that such services comply with the requirements of this section by signing the appropriate checklist(s) provided by the department.
    [Statutory Authority: Chapter 90.76 RCW. WSR 95-04-102, § 173-360-310, filed 2/1/95, effective 3/4/95; WSR 91-22-020 (Order 91-26), § 173-360-310, filed 10/29/91, effective 11/29/91; WSR 90-24-017, § 173-360-310, filed 11/28/90, effective 12/29/90.]
Chapter 90.76 RCW. WSR 95-04-102, § 173-360-310, filed 2/1/95, effective 3/4/95; WSR 91-22-020 (Order 91-26), § 173-360-310, filed 10/29/91, effective 11/29/91; WSR 90-24-017, § 173-360-310, filed 11/28/90, effective 12/29/90.

Rules

173-360-305,173-360-380,173-360-398,173-360-399,173-360-325,173-360-305,173-360-345,173-360-345,173-360-325,173-360-305,173-360-305,173-360-305,173-360-305,