Chapter 173-240. Submission of plans and reports for construction of wastewater facilities. |
Section 173-240-180. Approval of construction changes.
Latest version.
- All wastewater facilities subject to the provisions of this rule must be constructed in accordance with the plans and specifications approved by the department. Any contemplated changes during construction, which are significant deviations from the approved plans, must first be submitted to the department for approval.[Statutory Authority: RCW 90.48.110. WSR 00-15-021 (Order 00-09), § 173-240-180, filed 7/11/00, effective 8/11/00. Statutory Authority: Chapters 43.21A and 90.48 RCW. WSR 83-23-063 (Order DE 83-30), § 173-240-180, filed 11/16/83. Statutory Authority: RCW 90.48.110. WSR 79-02-033 (Order DE 78-10), § 173-240-180, filed 1/23/79. Formerly chapter 372-20 WAC.]
RCW 90.48.110. WSR 00-15-021 (Order 00-09), § 173-240-180, filed 7/11/00, effective 8/11/00. Statutory Authority: Chapters 43.21A and 90.48 RCW. WSR 83-23-063 (Order DE 83-30), § 173-240-180, filed 11/16/83. Statutory Authority: RCW 90.48.110. WSR 79-02-033 (Order DE 78-10), § 173-240-180, filed 1/23/79. Formerly chapter 372-20 WAC.